The Trump administration on Tuesday requested an additional $50.1 billion by Congress on top of the $12.5 billion previously allocated to complete a new air traffic control system.
The request, sent in a letter to House and Senate appropriators, follows the Nov. 13 nationwide ground stop in which the Federal Aviation Administration halted domestic departures for nearly five hours. Nearly 20,000 flights were canceled through Monday morning, according to the Wall Street Journal. It was the longest ground stop since Sept. 11, 2001.
The additional funding requests roughly $10 billion for each of the following: completion of a reliable digital architecture, overhauling of outdated airport infrastructure, modernizing aging airport terminals, five new consolidated air route traffic control centers to replace 22 "deteriorating" ones, and to build and improve up to 140 air traffic control towers.
The letter was signed by U.S. Department of Transportation Secretary Sean Duffy and FAA administrator Bryan Bedford.
The root cause for the ground stop officially remains undetermined, but FAA has connected disruption to the installation of a new router in El Dorado, Ark., by contractor L3Harris. The ground stop followed a flood of data in destabilized FAA's legacy equipment, disrupting 17 of its 22 air route traffic control centers and spreading to several terminal radar approach controls.
DOT and FAA then issued the ground stop "out of an abundance of caution … to ensure aircraft could continue to operate safely," according to the agencies. FAA has paused further installation of the new routers.
Brokerage company Bernstein estimated that Friday's ground stop cost the largest four U.S. airlines—American Airlines, Delta Air Lines, Southwest Airlines and United Airlines—about $345 million, according to Reuters.
The $50.1 billion funding request has been met with skepticism by members of Congress, with some noting that the first $12.5 billion hasn't been spent yet. A letter from several Democrats on the Senate Commerce Committee to Duffy and Bedford noted the funding request was $20 billion more than a request made last week.
Duffy in a Tuesday briefing responded that Congress had given "very specific categories" on which the agencies could spend the money. Equipment is on order, and when it gets delivered, it will get paid for, he said, adding that "I think the point here is all the money has been set aside for this mission of modernizing the airspace."
Duffy further noted: "Because our airspace is so big, we have so much equipment in the airspace. I can't go to, say, a Best Buy and just take it off the shelf. We actually have to order the equipment. And then the companies that get the contracts, they actually have to build the equipment for us to then take possession. … I only pay when they deliver."